Lakeview Village Administrator Pat Parish reported at the Monday evening village council meeting that work on the new fire station at 540 N. Main St. is ahead of schedule and drywall has been installed.
Fire Department Chief Norm Spring also asked council about the electric and air drops in the new fire house. It was not part of the original bid package, but is needed for each fire truck, he said.
Members approved a change order to include the drops for each truck, with a cost estimate of $3,000.